Arnold Clark Hire Drive – Manchester Airport 

Premac Group were engaged to provide full strip-out and refurbishment of an existing car hire facility. Our team reconfigured the ground and first floor layouts to accommodate additional WC’s, a more inviting reception as well as additional welfare facilities for staff. The scope included the provision of new ceilings, flooring, decoration, doors, lighting and electrical distribution throughout the facility.

“Another successful project delivered by Premac Group Ltd in a live working environment, works finished to a high standard, on-time and on budget”

S McLoone, Arnold Clark Estates Team

Duration – 16 Weeks
Value – £285,000